Current Projects:
Local Collector Evaluation and Rehabilitation Project.
Owner: CSU. Description as discussed on Wildcat Construction page.
48th and Tennyson/Lawrence Street Siphon Rehabilitation Project.
Owner: City and County of Denver.
Current Contract Value: $897,039.05
Installation of approximately 28,000 LF of various sized cured-in-place pipe for the City and County of Denver.
Project Completion: July 2009
Sanitary Sewer Emergency Rehabilitation.
Owner: City and County of Denver.
Current Contract Value: $495,000.00
Installation of point repairs and cured-in-place pipe in various locations throughout the Metro Denver area.
Project Completion: August 2009.
Other notable projects:
84” CIPP – Ranchmen’s Ditch – Grand Junction, CO.
Owner: City of Grand Junction; Prime Contractor: Mendez, Inc.
Contract Amount: $457,524.90
Installation of 561 LF of 84” CIPP.
Project Completion: March 2008.
Little Dry Creek Siphon Structure Rehabilitation.
Owner: City of Littleton; Prime Contractor: T Lowell Construction.
Contract Amount: $122,100.00
Installation of 170 LF each of 36”, 30” and 18” CIPP in a siphon pipe under Little Dry Creek.
Completion: December 2008.